Premier Inn, Hinckley
Full Roof Refurbishment
Roof Refurbishment
Premier Inn, Hinckley
Project Overview
We were appointed to deliver a comprehensive roof and external envelope refurbishment at Premier Inn Hinckley, covering approximately 1,900 m² of roof area. The objective was to replace the existing, end-of-life roofing system with a modern, high-performance solution, while improving ventilation, weather resistance, and long-term durability across the building.
Site Setup & Management
A full site compound was established to support the works, including designated welfare facilities, material storage areas, and controlled access points. A telehandler and qualified driver were in constant attendance to manage the safe and efficient movement of materials to roof level, significantly improving productivity and reducing manual handling risks.
A dedicated site manager was present on site daily to coordinate labour, manage health and safety compliance, and liaise with hotel management. The project manager carried out frequent site visits, attending a minimum of three times per week, ensuring programme adherence, quality control, and clear communication with all stakeholders throughout the duration of the works.
Scope of Works
Challenges & Solutions
The project was carried out within a live hotel environment, requiring careful phasing and sequencing to minimise disruption to guests and daily operations. Works were planned to maintain full weather protection at all times, with exposed areas kept to a minimum and closely monitored during periods of adverse weather.