Falkirk Football Stadium

Skylight replacement & new man safe system to the North Stand

Skylight replacement

Falkirk Football Club

The Works

The project at Falkirk Stadium, involved the replacement of skylights and installation of a new man safe system to the North Stand. The primary objective was to deliver the works safely, efficiently, and ahead of schedule while ensuring zero disruption to ongoing club operations, including match days and training sessions. Careful pre-construction planning was carried out to align the schedule with stadium activities, supported by strong communication with the club’s management team. The use of temporary scaffolding and safety nets ensured the highest safety standards for both operatives and the public, while lightweight, durable roofing panels were selected to facilitate a faster and safer installation process.

Through clear coordination, proactive planning, and a dedicated focus on safety and efficiency, the project was completed two weeks ahead of programme. There were zero safety incidents reported throughout the duration of the works. The final outcome delivered a robust, modern roofing structure, clearly visible in aerial images of the North Stand, reflecting the team’s commitment to precision and quality workmanship.

Client Name
Falkirk Football Club
Scope
Skylight replacement
Sector
Sports & Leisure
Program
8 Weeks
Value
£164k
  • Main Objective Deliver safely efficiently & ahead of schedule
  • Project Goals Ensure no disruption to ongoing club activities and match days. Deliver the project ahead of program. Maintain the highest safety standards throughout the works
  • Planning Careful pre-construction planning to align with the stadium’s schedule and minimize public disruption. Access & Safety Temporary scaffolding and safety nets installed to ensure operative’s and public safety. Materials Use of lightweight, durable roofing panels to speed up installation. Coordination Regular updates with Falkirk FC management to align on matchdays and training schedules, progress reports submitted weekly
  • Key Achievements Delivered Ahead of Program. Completion achieved 2 weeks earlier than projected. No accidents or safety breaches throughout the works.

What Our Client Said….

“After a competitive tender process RML Roofing were appointed by Falkirk FC to replace part of the North Stand roof at the Falkirk Stadium. They provided excellent technical advice as to the best solution for the works which was adopted by us. The works process was excellently managed by Ian Gordon and his team and went completely to program. As a client we were kept completely up to date with site progress throughout the process. Health and Safety was a priority at all times given we were able to maintain stadium access throughout as well as accommodate a club fixture seemlessly during the works. As a veteran of 35 years in the contracting world I can honestly say that RML Roofing have been an excellent organisation to work with.”

Bob Leishman, Director Falkirk FC